As part of the wider Catcher contract in 2016, Altus Intervention was required to provide engineering, equipment and personnel in order to complete the full onshore pre-commissioning of three bundles (Catcher, Burgman and Varadero) on a tight, two-month schedule prior to launch.
An efficiently executed solution utilising dedicated teams and equipment to complete a significant number of operations within schedule completing the task with 16,600 personnel-hours and 19 wagonloads of equipment
The completion of the pre-commissioning scope at Wester Site led to the launch of one of the operator's most successful projects, with the delivery of three bundles to the Catcher field.