Case Study:

Pipeline & Process

De-Commissioning Project

Country:
UK
Year:
2017
Technologies:
Helium Leak Test Pack Engineering & Helium Leak Testing, Purge Pack Engineering & Purging, Bolt Torquing & Tensioning, Flange Management

  • Multi-disciplined crew ensures cost savings for the client
  • 35 day campaign

CHALLENGE

Altus Intervention were contracted by the operator to carry out process services for their platform de-commissioning project.

 

SOLUTION

Altus Intervention utilised a multi-disciplined crew to initially purge the process plant evacuating all hydrocarbons. The same multi-skilled personnel then proceeded to undertaking the bolting operations to remove and blind off trees and flowlines in readiness for the plugging and abandoning phase. Leak testing was carried out on re-routed pipework.

 

RESULTS

Utilising a multi-disciplined crew ensured cost reduction due to minimal crew rotation & shortened delivery schedule.

FIND OUT MORE

TALK TO OUR EXPERTS